22-2017 Mayor's Request Approved

Requesting authorization to borrow $89,332,819 in a bond, and to appropriate the same amount for the Poplar Street Pump Station construction project.

From
Engineering
Introduced
Nov 17, 2022
Assigned to
City Council
Enactment #
214709

History

  1. Dec 15, 2022
    City Council Mayoral Approval
  2. Dec 8, 2022
    City Council Approved · roll call: pass Meeting agenda, item 6.D.12.
  3. Dec 6, 2022
    Finance Recommended to be approved · roll call: pass Meeting agenda, item 5.
  4. Nov 22, 2022
    City Council Referred for recommendation · roll call: pass

    Finance Committee

    Meeting agenda, item 7.2.

Official text

To the Honorable City Council: The Mayor respectfully requests that this Council appropriate $89,332,819 in order to fund the Poplar Street Pump Station project interim guaranteed maximum price (IGMP) 1 and 2 for the construction manager at-risk (CM@R). IGMPs 1 and 2 include but are not limited to soil excavation and disposal, storage tank installation, pump house equipment, force main, site borings, site preparation, pump house construction, and influent screening equipment. To meet this appropriation, the Treasurer will be authorized to borrow $89,332,819 as provided by MGL Chapter 44. Debt service will be paid from the Sewer Enterprise Fund. Appropriate staff will be available to answer any questions about this bond you may have. Thank you for your consideration of this matter. Respectfully, Katjana Ballantyne, Mayor