22-2017 Mayor's Request Approved
Requesting authorization to borrow $89,332,819 in a bond, and to appropriate the same amount for the Poplar Street Pump Station construction project.
- From
- Engineering
- Introduced
- Nov 17, 2022
- Assigned to
- City Council
- Enactment #
- 214709
History
-
Dec 15, 2022
City Council Mayoral Approval
- Dec 8, 2022
- Dec 6, 2022
-
Nov 22, 2022
City Council Referred for recommendation · roll call: pass
Finance Committee
Meeting agenda, item 7.2.
Official text
To the Honorable City Council:
The Mayor respectfully requests that this Council appropriate $89,332,819 in order to fund the Poplar Street Pump Station project interim guaranteed maximum price (IGMP) 1 and 2 for the construction manager at-risk (CM@R). IGMPs 1 and 2 include but are not limited to soil excavation and disposal, storage tank installation, pump house equipment, force main, site borings, site preparation, pump house construction, and influent screening equipment. To meet this appropriation, the Treasurer will be authorized to borrow $89,332,819 as provided by MGL Chapter 44. Debt service will be paid from the Sewer Enterprise Fund.
Appropriate staff will be available to answer any questions about this bond you may have. Thank you for your consideration of this matter.
Respectfully,
Katjana Ballantyne, Mayor